Taking a little time to cut a lot of carbon

One of the myths about using GGBS to cut cement use is that its inclusion in a project leads to long delays on site — in particular, unfounded anxieties rise during cold weather, and when ambitious cement substitution levels are attempted.

Yet with close collaboration between architect, contractor, concrete supplier and Ecocem, the Western Region Garda Headquarters in Galway set about debunking myths — substituting up to 65% of cement with GGBS during winter pours, with barely noticeable time increases.

Standing opposite ATU on the old Dublin road into Galway, the new Garda HQ is a striking limestone and granite complex that includes the full range of Garda facilities — from secure detention areas, conferencing and incident management facilities to a basement firing range for training. Built by JJ Rhatigan, it was designed by the OPW’s Architectural Services team, led by then State Architect, Ciaran O’Connor.

O’Connor began specifying GGBS in public buildings in 2010. Its technical properties offered an obvious advantage, but it was its sustainable credentials that he felt were unarguable. “It was such an obvious win,” he said. “To me, it was just so self-evident. Why would you pass that opportunity by?”

Critically, the OPW doesn’t build and hand over. It continues to manage the 2,400 buildings on its books, so it’s got a vested interest in durable, low maintenance structures. Against that backdrop, having confidence in your building materials and practices is absolutely vital.

“We don’t have insurance”, says O’Connor. “We carry our own risk. So if we goofed on that, we’d know pretty quickly, because we’d have to pay to fix it…you learn fast what does and doesn’t work.”

Throughout his time as State Architect, he would often field calls from engineers asking if it was true that he was using GGBS. “And I’d say yes, and that was a comfort to them…people felt, okay, we’re not taking a jump
into the unknown.”

Once you go above a certain percentage of GGBS, concrete can take a little longer to achieve early stage strength but this doesn’t mean delays are inevitable.

When the architectural services team at the OPW specified the Garda Western HQ project, they included a requirement for additional propping time and planned the project around this basic need.

O’Connor agrees that knowing exactly what’s required at the outset, and programming creatively around that means that you can design away potential delays.

Innovative Athenry-based concrete supplier Coshla Quarries provided all in situ concrete for the project, along with stone for aggregate. This included high strength structural C40/50 concrete for the slab foundation — which integrated 65% Ecocem GGBS in spite of the pour starting in February 2016. Meanwhile the external walls were also poured in situ concrete, using C30/37 concrete integrating 50% GGBS, again during winter pours.

Coshla Quarries general manager Martin Collins is matter of fact about the impact the GGBS had. “When the weather was cold they just left the shutters on for an extra day. It wouldn’t have slowed it down. it just
meant more shutters on site.”

The result speaks for itself and use of GGBS has become part of the OPW’s standard palette of materials, and now features in a long list of public buildings, including other recent Garda projects at Kevin Street and Military Road in Dublin.